Industrial Construction
Production building for an electronics components plant
A steel-frame production building delivered from design support through construction, with a schedule planned so the adjacent operating plant was never disrupted.
- Client
- Japanese electronics manufacturer
- Location
- Bac Ninh, Vietnam
- Period
- Mar 2024 – Nov 2024
- Scale
- 12,000 m² floor area